| |
|
|
Advertisement
for bid
Opening of Contractors bids
Evaluation of bids completed
Notice of Award
Notice to Proceed
Begin Construction |
July 7, 2005
Aug 5, 2005
August 26, 2005 *
September 6, 2005 *
September 26, 2005 *
October 24,2005 |
| |
|
| *
Dates are approximate, depending on approval process. |
|
| |
|
|
|
| Fall-Winter
2005 |
| |
|
|
|
Begin
Utility Adjustments.
Begin
Construction of Pedestrian Underpass.
Construct Temporary Pavement.
Install Temproary Traffic Signals.
Install Proposed Storm sewers and Water main.
|
|
| |
|
| Spring-Summer
2006 |
|
| |
|
| |
Install Proposed Storm sewers and Water main.
Remove existing SB Randall Rd. and EB IL 64 outside
lanes.
Continue construction of Pedestrian Underpass.
Topsoil restoration adjacent to completed work. |
|
| |
|
| Summer-Fall
2006 |
| |
| |
Continue installation of Proposed Storm sewers and Water main.
Construct new SB Randall Rd. and EB
IL 64 outside lanes.
Complete landscape restoration adjacent to completed
work.
Stage traffic to outside lanes.
Remove existing NB Randall Rd. and EW IL 64 outside
lanes.
Topsoil restoration adjacent to completed work. |
| |
|
| Fall-Winter
2006 |
|
| |
|
| |
Complete Pedestrian Underpass.
Continue installation of New Roadway Lighting and Traffic Signals.
Continue installation of Proposed Storm sewers and Water main (Stage 2). |
| |
|
|
Spring-Summer 2007
|
Construct new NB Randall Rd. and WB
IL 64 outside lanes.
Continue landscape restoration adjacent to completed
work.
Remove remaining center pavement and complete median construction
|
| Summer-Fall 2007 |
Remaining
schedule to be determined
upon evaluation of work completed
to date. |
| |
|
| |
|
| |
|