Randall Road & Illinois Route 64 Intersection Improvement
       
       
       

Project Timeline


Advertisement for bid

Opening of Contractors bids

Evaluation of bids completed

Notice of Award

Notice to Proceed

Begin Construction

July 7, 2005

Aug 5, 2005

August 26, 2005 *

September 6, 2005 *

September 26, 2005 *

October 24,2005

   
* Dates are approximate, depending on approval process.  
   
 
Fall-Winter 2005
   
  Begin Utility Adjustments.
Begin Construction of Pedestrian Underpass.
Construct Temporary Pavement.
Install Temproary Traffic Signals.
Install Proposed Storm sewers and Water main.
 
   
Spring-Summer 2006  
   
 

Install Proposed Storm sewers and Water main.
Remove existing SB Randall Rd. and EB IL 64 outside lanes.

Continue construction of Pedestrian Underpass.

Topsoil restoration adjacent to completed work.

 
   
Summer-Fall 2006
 
 

Continue installation of Proposed Storm sewers and Water main.

Construct new SB Randall Rd. and EB IL 64 outside lanes.
Complete landscape restoration adjacent to completed work.
Stage traffic to outside lanes.

Remove existing NB Randall Rd. and EW IL 64 outside lanes.

Topsoil restoration adjacent to completed work.

   
Fall-Winter 2006  
   
 

Complete Pedestrian Underpass.
Continue installation of New Roadway Lighting and Traffic Signals.

Continue installation of Proposed Storm sewers and Water main (Stage 2).

     

Spring-Summer 2007

 

 

 

Construct new NB Randall Rd. and WB IL 64 outside lanes.

Continue landscape restoration adjacent to completed work.

Remove remaining center pavement and complete median construction

Summer-Fall 2007 Remaining schedule to be determined upon evaluation of work completed to date.
   
   
 

 