Update: Sept 24, 2007 (8:00 am)
Randall Road --
PLEASE PROCEED THRU THE WORK ZONES WITH CAUTION.
Planned work for the week includes
Randall Road - Excavating and grading for the bike path to the north of Dean St. on the west side. Excavating for an electric duct along the west side between Dean St. and the bike/pedestrian underpass. Adjusting structures in the asphalt pavement. Placing top soil for the proposed landscaping between IL 64 and Oak St. Placing concrete for an adjustment in the concrete pavement. Landscaping work is scheduled to begin mid-week.
IL Rte 64 - Final preperations for surfacing. Landscaping work is scheduled to begin mid-week.
Dean Street - Final preperations for surfacing. Landscaping work is scheduled to begin mid-week.
Randall Road traffic is now in full Stage III configuration with traffic split to the east and west sides of the road utilizing new pavement.
Traffic on IL 64 within the project limits is split to the north and south sides of the roads utilizing new pavement.
Dean Street is in the proposed final lane configuration.
|