Update: Oct 2, 2007 (8:30 am)
Randall Road --
PLEASE PROCEED THRU THE WORK ZONES WITH CAUTION.
Planned work for the week includes
Randall Road - Grading and placing asphalt for the proposed bike path between the bike/pedestrian underpass and Dean St. Planting trees, plantings, and sodding for the medians between Dean St. and IL 64 and IL 64 and Oak St. Planting seeding and installing erosion control blankets along the east side between IL 64 and Oak St. Placing asphalt for final surface set to begin at the end of the week. Excavating and placing concrete for sidewalks in the southeast corner at Il 64. Turning on permanent traffic signals at IL 64.
IL Rte 64 - Placing asphalt for final surface set to begin at the end of the week. Planting sodding/seeding and installing erosion control blankets along the north side within project limits. Turning on permanent traffic signals at Randall Rd.
Dean Street - Placing asphalt for final surface set to begin at the end of the week.
Randall Road traffic is now in full Stage III configuration with traffic split to the east and west sides of the road utilizing new pavement.
Traffic on IL 64 within the project limits is split to the north and south sides of the roads utilizing new pavement.
Dean Street is in the proposed final lane configuration.
|