Randall Road & Illinois Route 64 Intersection Improvement
         
         
         

Update for Week of October 22, 2007

Update: Oct 22, 2007 (8:30 am)

Randall Road --

PLEASE PROCEED THRU THE WORK ZONES WITH CAUTION.

Planned work for the week includes

Randall Road - Completing pavement markings for the proposed final traffic configuration. Placing asphalt for the bike path along the west side north of Dean St. and for the UPRR crossing. Placing concrete for sidewalks in the southeast corner at IL 64 and for minor repairs to median curb and gutter at IL 64.

IL Rte 64 - Completing installation of recessed pavement markings within project limits.

Dean Street - Completing pavement markings for the proposed final traffic configuration.

Randall Road traffic is now in full Stage III configuration with traffic split to the east and west sides of the road utilizing new pavement.

Traffic on IL 64 within the project limits is split to the north and south sides of the roads utilizing new pavement.

Dean Street is in the proposed final lane configuration.

 
Update Headlines
Weekly update for October 15, 2007
Construction Update
Weekly update for October 8, 2007
Construction Update
Weekly update for October 1, 2007
Construction Update
Weekly update for September 24, 2007
Construction Update

 


 

© Copyright 2005 V3 Companies, All Rights Reserved. last updated: Oct 22, 2007